Subcontracting in Tenders: How It Works and What to Disclose

Subcontracting in a tender means the company that wins a public contract hands part of the work to another company while staying fully responsible for the result. If you bid as a prime, you name your subcontractors where the buyer asks, flow your obligations down to them and answer for their mistakes. If you bid as a subcontractor, you win through the prime, not through the buyer. The rules differ by country and by contract size, so this guide covers the US first, then the EU, the UK and a few other markets.
TL;DR
- A subcontractor performs a portion of a contract the prime has won. The buyer contracts with the prime only, and the prime stays liable for everything its subcontractors do.
- Buyers can ask you to state in the tender which share you plan to subcontract and to whom. Some require signed letters of intent from each subcontractor.
- In US federal work, a formal subcontracting plan applies to larger contracts: above $900,000, or $2 million for construction, when subcontracting possibilities exist. Large businesses are the ones who typically have to file one.
- Failing to make a good faith effort to meet a plan can lead to liquidated damages.
- Choose subcontractors on capability, finances, compliance and delivery risk, and manage them under a written contract with regular reporting.
Table of Contents
- What subcontracting means in a public tender
- Why supply chain matters to your bid
- What you must disclose to the buyer
- US federal rule: the subcontracting plan
- Limits buyers can place on subcontracting
- How to choose and price subcontractors
- Managing subcontractors after the award
- Our perspective
- Where Better Presence fits
- FAQ
- Sources
What subcontracting means in a public tender
In plain terms, a subcontractor is a business that supplies goods, works or services to perform a slice of a contract held by someone else. The Asian Development Bank describes it as a supplier that has a contractual arrangement with a main contractor to perform a portion of the contract. The same guidance says subcontracting matters at every stage of a procurement: planning, prequalification, bidding, evaluation, award and delivery.
The OECD SIGMA brief gives a similar definition: an operator awarded a public contract entrusts another entity with part of the works or services. It adds that subcontractors may themselves subcontract parts of their work, which creates tiers.
Two points shape everything else:
- One contract, one counterparty. The buyer contracts with the bidder and has no legal relationship with the subcontractor. The prime is responsible for its subcontractors’ performance, and using them does not relieve the contractor of its obligations.
- Success is shared. The NDIA’s prime/subcontractor framework describes a relationship in which each party’s success depends on the other’s, with open communication as a key ingredient.
That is also why subcontracting is such a practical route for smaller companies. A small firm may not meet a tender’s capacity or turnover requirements alone, but it can deliver a defined package inside a larger firm’s bid. Equally, a small prime can win a contract bigger than its own headcount by bringing in specialists for parts it does not cover.
Why supply chain matters to your bid
People searching for supply chain tenders are usually asking the same question from the other side: how do I get into a prime’s supply chain, or how do I build one for a bid? Both come down to the same thing. The tender is evaluated as one package, and the buyer wants to see that every part of the delivery is covered by a business that can do it.
For a prime, the supply chain feeds the bid in three ways:
- Capacity and capability. Subcontractors fill gaps in skills, equipment, certifications or geography.
- Price. Subcontract quotes feed directly into your bid price. Research on tender practice has long noted that contractors rely on subcontract and supply enquiries to calculate their bid prices, which is why early, clear enquiries to subcontractors improve the accuracy of your price.
- Credibility. Named, qualified partners show the buyer that delivery is planned, not hoped for.
For a subcontractor, the entry point is the prime’s bid process. Primes build teams while the tender is open, so being known to them before a solicitation is published matters more than reacting after it is.
What you must disclose to the buyer
What a tender must say about subcontracting depends on the buyer and the jurisdiction. The common pattern is that the buyer may ask you to identify your subcontractors and the share of work they will do.
In the EU, Directive 2014/24/EU Article 71(2) permits contracting authorities to ask a bidder to indicate any share it intends to subcontract and any proposed subcontractors. The European Medicines Agency’s guidebook for tenderers shows what that looks like in practice: if the tender envisages subcontracting, it must include a document stating the names, addresses and registration numbers of the subcontractors, their roles and responsibilities, and the volume or proportion subcontracted, plus a signed letter of intent from each.
The UK works similarly. Under the Public Contracts Regulations 2015, regulation 57 lets authorities ask suppliers to indicate whether they intend to subcontract and to name subcontractors, and authorities may check whether exclusion grounds apply to them. After award, the supplier must tell the authority about any subcontractors not previously identified, at the latest when the contract starts, and report any later changes.
A practical disclosure checklist for any tender:
| Item | Why the buyer wants it |
|---|---|
| Legal name, address, registration number | To check eligibility and exclusion grounds |
| Scope of the subcontracted work | To confirm the prime keeps the core delivery |
| Share of the contract value or volume | To test against any cap or minimum |
| Signed letter of intent | To show the subcontractor is committed |
| Change-notification process | To keep the record accurate during delivery |
Always read the instructions to tenderers first. Some buyers ask for this at bid stage, others only after award, and a missing form can cost you the evaluation points or the bid itself.
US federal rule: the subcontracting plan
In US federal procurement, the document people mean is the subcontracting plan. Under FAR 19.702, in negotiated acquisitions each solicitation expected to exceed $900,000 ($2 million for construction) and with subcontracting possibilities requires the apparently successful offeror to submit an acceptable plan. If the selected bidder does not submit it in time, the bidder becomes ineligible for award.

The requirement is aimed at large businesses. Small businesses are generally not asked to file one, but they are on the receiving end of the goals the plan sets. That is a real opening: a large prime must describe how it will give small businesses a fair opportunity, so it has a reason to find qualified small subcontractors.
The Department of Defense’s guidance lists 15 mandatory elements of a subcontracting plan. They include:
- Separate dollar goals for each small business category.
- A description of the principal supplies and services to be subcontracted.
- A description of the method used to identify potential small business sources.
- Flow-down clauses on small business use.
The plan has teeth. When a contractor fails to make a good faith effort to comply, liquidated damages are payable, and the contracting officer looks at the totality of the contractor’s actions. The takeaway for primes is to track subcontract spend as you go, not at the end.
State programs can add their own versions. In Texas, for example, solicitations where subcontracting is probable require a HUB subcontracting plan with a good faith effort certification, identified subcontractors, the expected percentage subcontracted and its approximate dollar value, as the EMA guidebook summarizes. Check your state’s procurement rules for equivalents.
Limits buyers can place on subcontracting
Not every buyer lets you pass work down freely. The EU directive includes a specific limit: for works, services and installation operations, authorities may require that certain critical tasks be performed directly by the tenderer and not subcontracted.
National rules vary widely, according to the FIEC’s 2026 report on construction subcontracting in Europe:
- France: a 1975 law regulates subcontracting on public and private contracts, with no limit on tiers, but each subcontractor must be accepted by the contracting authority and its payment terms approved.
- Italy: under Article 119 of the Public Procurement Code, full subcontracting is prohibited and the main contractor must perform the predominant part of the works, with no fixed quantitative caps after the 2023 reform.
- Croatia: a lawyer quoted in Lider Media in 2026 welcomed liberalized subcontracting, arguing the winner has provided guarantees and is accountable, so the choice of cooperators is a business matter.
- Manitoba, Canada: for contracts tendered after March 31, 2016, subcontractors worth C$100,000 or more must hold a recognized safety program certification.
The lesson for a cross-border bidder is simple: never assume that what worked in one country carries over. Read the tender documents for caps, required self-performance and approval steps.
One more UK point is useful when you are naming a supply chain. NEC Contracts explains that a buyer should not force the supplier to use specific subcontractors in the buyer’s own scope. Instead, buyers can require suppliers to name their supply chain in the supplier’s scope, and the winner must then use those named firms. So the names you put in your bid can become binding.
How to choose and price subcontractors
The RICS subcontracting guidance treats this as a procurement exercise of its own. Your strategy should divide the main works into subcontract packages and set requirements for scope, quality, time and cost, assessed against risk. A well-drafted strategy helps you obtain suitable, well-considered tenders from the subcontract market.
A workable process:
- Split the scope into packages. Define what each package includes, the deliverables and the dates. Vague packages produce vague quotes.
- Issue the same enquiry to several candidates. Include the buyer’s requirements that will flow down: insurance, certifications, reporting and payment terms.
- Assess more than price. Look at capability, references, financial stability, safety record and labor practices. Guidance on negotiating engineering services contracts shows how scope and responsibilities get settled before work starts.
- Check the compliance requirements. Obligations placed on the contractor, such as health and safety, eligibility, environment and labor rules, should also bind subcontractors by law or contract.
- Secure a letter of intent before you submit. Many buyers ask for one, and it protects your price.
- Keep a fallback. If a named subcontractor drops out, your bid assumptions change.
Managing subcontractors after the award
Winning is where the liability begins. The ADB identifies risks to schedule, quality and cost from subcontractor underperformance, insolvency, disputes or incompetence, and supply-chain integrity risks such as child labor, forced labor and unsafe conditions. It recommends including subcontractors in contract management meetings and reporting.
The CECA’s NEC4 bulletin gives practical advice for the contractor’s side of the relationship. It says to make expectations clear at tender stage and look for evidence that the subcontractor understands the rules and principles of the contract. It also suggests treating subcontractors as you would want the client to treat you:
- Do not rely on verbal instructions.
- Respond to submissions well within contractual timescales.
- Agree change promptly.
- Do not let a lack of agreement with the client hold up agreement with the subcontractor.
The working relationship between a prime and its subcontractors is also a delivery-model question that owners weigh when comparing contracting approaches. Whichever model the buyer picks, your internal discipline decides whether the subcontract chain holds.
For larger programs, build in a risk register, escalation routes and contingency plans. The UK Department for Education’s standard for post-16 providers, which applies to subcontracting of £100,000 or more, requires clear risk responsibilities, regular monitoring, escalation routes and exit strategies. It is a UK education rule, but the structure is a good model for any prime.
Our perspective
Most small companies we speak to think of tenders as a single, heavy document that someone else writes. In reality, a tender is a bundle of smaller decisions: which opportunities fit, who needs to be named, which forms must be signed and which certificates must be attached. Subcontracting adds more of those decisions, and each one is a place where a good bid quietly falls apart.
We built Better Presence for SMEs that have no bid team. Our platform is designed to check eligibility, score how winnable an opportunity is, assemble the documents and handle multi-language compliance, so that an owner or CFO can decide where to bid instead of drowning in paperwork. Everything stays under the customer’s control, and because we charge a flat subscription with no success fees, whatever you win stays with you.
Our view is that subcontracting should not be a reason a small firm skips a tender. It is one of the best ways to bid above your weight, provided the paperwork around it is done properly and on time. Spend your hours on the partnerships and the delivery plan. Let software carry the forms.
Matevz
Where Better Presence fits
If you are bidding as a prime, your time is better spent on subcontractor selection and pricing than on hunting for notices and assembling forms. Better Presence automates discovery, eligibility matching and application preparation for public grants, tenders, awards and supplier registers across Europe, with winnability scoring and document assembly built in.

Plans are published as flat subscriptions: Presence at €149 per month or €1,490 per year, Pipeline at €349 per month or €3,490 per year, Growth at €649 per month or €6,490 per year, and Group from €1,200 per month. You can see what each includes on the Better Presence plans page.
FAQ
What is subcontracting in simple terms?
Subcontracting is when the company that wins a contract pays another company to do part of the work. The buyer deals only with the winner, who stays responsible for quality, delivery and compliance. The subcontractor answers to the winner, not to the buyer.
What is the rule of two in government contracting?
We could not tie that phrase to the sources used in this guide, so we do not define it here. For US federal work, the subcontracting rules to read are FAR subpart 19.7 and your solicitation’s instructions, and a contracting officer or your local Procurement Technical Assistance Center can confirm how they apply to your bid.
Do I have to name my subcontractors in a tender?
Only if the buyer asks. Under EU and UK rules, authorities are permitted to require you to indicate the share you intend to subcontract and the proposed subcontractors. Some tenders also want signed letters of intent, so check the instructions to tenderers.
When is a subcontracting plan required in a US federal bid?
Under FAR 19.702, for negotiated acquisitions expected to exceed $900,000, or $2 million for construction, with subcontracting possibilities, the apparently successful offeror must submit an acceptable plan. Thresholds are adjusted over time, so confirm the current figure in the FAR and in your solicitation.
Who is liable if a subcontractor fails?
The prime. Using a subcontractor does not relieve the contractor of its obligations to the buyer. That is why flow-down clauses, regular reporting and fallback options belong in your bid plan.
Sources
- ADB Guidance Note on Procurement: Subcontracting
- OECD SIGMA brief: Subcontracting
- NDIA Prime/Subcontractor Collaboration Framework
- Subcontract and supply enquiries in the tender process
- EMA Guidebook for Tenderers
- UK Procurement Pathway: finalise and publish procurement pack
- UK Procurement Pathway: contract award and implementation
- FAR 19.702 Statutory requirements
- FAR 19.705-7 Compliance with the subcontracting plan
- DoD: The Basics of Subcontracting plans
- FIEC DESOCO 3 final report
- Lider Media: public tender winner can delegate the entire job
- Manitoba Government Wide Contract Policy FAQ
- NEC Contracts: bid-winning supply chains
- RICS Subcontracting guidance note
- CECA NEC4 Bulletin No. 20: Managing Subcontractors
- UK DfE subcontracting standard